On any structural project large enough to involve an owner's inspection representative, a government agency, or an AISC-certified fabricator, you will encounter the inspection test plan. The ITP is not an AWS D1.1 document—the code does not use that term—but it is the operational backbone that makes D1.1 compliance auditable and sequenced for a real production environment.
Understanding the ITP as a document type, and how it connects to your WPS and NDE documentation, is practical knowledge for any QC manager running a structural steel fab shop.
What an ITP Is and Is Not
A quality control plan (QCP) is a general policy document. It describes what the shop's quality program includes: its organization, document control approach, calibration program, nonconformance reporting system, and reference to the codes it works under. A QCP answers "what does your quality system cover?"
An inspection test plan is more granular and project-specific. It answers "at each step of fabricating this specific structure, who does what inspection, when, and what do they do if it fails?" The ITP is keyed to the production sequence—raw material receipt, fit-up, preheat, welding, post-weld NDE, dimensional check, final coating—and assigns an inspection activity and a sign-off level to each step.
The distinction matters because a QCP can be a static document that rarely changes, while an ITP is tailored to the project, the governing code, and the owner's inspection requirements.
Structure of a Welding ITP
Most welding ITPs follow a tabular format with columns for:
- Activity / Description: The specific fabrication or inspection activity (e.g., "Pre-weld fit-up inspection of CJP groove joints").
- Reference document: The WPS number, code clause, or NDE procedure being applied.
- Acceptance criteria: The standard against which the activity is evaluated (AWS D1.1:2025 visual acceptance criteria, RT acceptance criteria, etc.).
- Responsible party: Fabricator QC, contractor QC, owner/third-party inspector, or some combination.
- Hold / Witness / Review: The notification level for each party.
- Record: What document is generated (inspection report, radiograph, test record).
The hold/witness/review distinction is the core of the ITP. It is the mechanism by which the owner's inspector maintains oversight without being present for every weld in a large fab shop.
Hold Points in Structural Welding
A hold point is a hard stop. Production cannot proceed past that stage until the designated party reviews the work and signs the ITP. Common hold points in structural welding programs:
Material receiving. Verification that the base metal CMTRs match the specified grade and heat number, and that the material meets dimensional and surface quality requirements. An owner's inspector may hold the right to review CMTRs before any material is cut.
First-article fit-up inspection. On repetitive weld assemblies, the first piece is a hold so the inspector can verify that the joint design matches the WPS and that fit-up tolerances are within AWS D1.1 requirements before the shop runs a full production run.
Preheat and interpass verification on critical or CVN-required joints. Where the WPS requires minimum preheat per Table 6.6 or where Table 6.8 supplementary essential variables apply, some owners hold preheat verification on the first joint of a heat or joint type.
NDE acceptance before backgouging or back welding. On CJP groove welds requiring backgouging to the root, the ITP may hold the back side until the root pass on the initial side passes RT or UT, and the backgouge is inspected visually before the back pass is applied.
Final NDE review before paint or coating. Owner inspector sign-off on the RT/UT/MT/PT reports before the coating crew covers the welds.
See CWI Inspection Hold Points in Structural Fabrication for detailed guidance on what each hold-point inspection covers.
Witness Points and Notification Windows
A witness point is less restrictive. The inspector must be notified in advance (typically 24–72 hours, as specified in the contract) and given the opportunity to attend. If the inspector waives attendance or does not appear within the notification window, work may proceed—but the notification record (date, time, who was notified) must be documented.
Typical witness points in structural fabrication:
- Preheat and in-process temperature monitoring.
- Welder identification stamp application on weld joints.
- Production welding of non-critical weld joints.
- Dimensional inspection of completed assemblies before delivery.
The practical implication: for witness points, the shop's CWI or QC inspector typically performs the inspection regardless of whether the owner's inspector attends. The shop's records document compliance; the owner's inspector reviews those records at the next review point or audit.
Review Points
A review point is the least demanding category. It means the inspector is entitled to review a specific document at some stage—but the activity itself can proceed without waiting for that review. Review points typically cover routine paperwork: WPS records, PQR records, welder qualification records, material certifications.
At the start of a project, an owner's inspector will often conduct a document review session where they review the shop's WPS/PQR library, welder qualification records, and QC plan against the project spec. That initial review is typically a review point (or sometimes a hold point before any production welding begins). Once approved, routine production welding proceeds without further document holds.