AISC Chapter N of the Specification for Structural Steel Buildings (AISC 360) sets quality control and quality assurance requirements for structural steel fabrication and erection. It assigns specific responsibilities to the fabricator's QC staff and to the owner's independent QA inspector, and it requires the fabricator to operate a documented QC program.
What Chapter N does not hand you is a project-specific welding quality plan. That document — the one that translates the general QC program into specific, actionable requirements for a particular building or structure — must be assembled by the fabricator's CWI or QC manager for each job.
This article describes the components of that plan, why each one matters, and how to assemble them before the first arc strike.
Why a Project-Specific Plan Matters
A fab shop's general QC program documents how the shop handles welding in the abstract: what process the shop uses, how WPSs are controlled, how welders are tracked. It is written for AISC certification maintenance, not for a specific job.
A project welding quality plan answers different questions: Which of our existing WPSs applies to the moment connections on this building? Are those WPSs within the code and project specification for this work? Which of our qualified welders are assigned, and are their qualifications current? What NDE method is the contract calling for on CJP groove welds, and at what coverage rate?
These questions need written answers before production, not during. When a third-party inspector arrives on the first day of welding, they should be able to review the quality plan and confirm that the welding program is set up correctly — before a single weld is made.
Component 1: WPS Applicability Matrix
The first and most critical component is a matrix showing which WPS applies to each weld type on the project. At a minimum, this should list:
- Weld types present on the project (CJP groove, PJP groove, fillet welds by size, stud welds)
- The WPS number applicable to each
- Process and filler metal used under each WPS
- Prequalified or tested (PQR reference number for tested WPS)
- Any project-specific supplements or restrictions called out in the specification
For seismic projects, the matrix must identify which welds are demand-critical and confirm that the applicable WPS and filler metal meet the CVN toughness requirements of AWS D1.8.
The WPS applicability matrix is often the first thing an AISC auditor or special inspector asks to see. Shops that cannot produce it quickly signal that their quality program is administrative rather than operational.
Rule library based on AWS D1.1:2025; verify against your governing edition.
Component 2: Qualified Welder and Operator Roster
AWS D1.1 Clause 6 requires that welding be performed by qualified welders — individuals who have passed a welder performance qualification test (WPQ) for the process, position, and base metal applicable to the work. The plan must list the welders assigned to this project with:
- Name and identification number
- WPQ test date and testing organization
- Qualified process(es) and position(s)
- Last production welding date (to confirm the six-month continuity rule is met)
- Any special qualifications (CVN filler metal handling, demand-critical weld qualification)
Welder continuity is a specific obligation: under AWS D1.1, a welder who has not welded in a given process for six months must requalify for that process. A project quality plan that shows current continuity dates for all assigned welders demonstrates the shop is actively managing this requirement. Projects that fail AISC audits on welder qualification almost always lack this documentation, not the actual qualification records.
Component 3: NDE Scope and Method Plan
The project's NDE requirements come from two sources: AWS D1.1 minimum requirements and any additional requirements imposed by the project specification, the owner, or the contract.
The NDE plan should specify:
- Which weld types require NDE, and which method (UT, RT, MT, PT, or visual only)
- Coverage percentage for each weld type
- The AWS D1.1 acceptance criteria applicable to each method
- Whether AISC seismic requirements or owner specifications call for additional coverage
- NDE timing (pre-NDT delay for hydrogen diffusion on high-strength steels, post-PWHT where applicable)
- Personnel qualifications (Level II UT or RT technicians, specific certifications required)
For many structural projects, visual examination per AWS D1.1 Clause 6 is the primary inspection method, with UT or MT added for CJP groove welds in tension or seismic demand-critical joints. The plan makes this explicit rather than leaving NDE decisions to the individual CWI.