5 min read

AWS D1.1:2025 Minimum Preheat: Table 5.11 Guide

How to read AWS D1.1:2025 Table 5.11 minimum preheat: pick the category, find the thickest part, handle mixed joints, and document it on your WPS.

New to procedures? Start with WPS welding: what a welding procedure specification is, with a filled-in example.

Preheat is one of the most checked and most misquoted numbers on a WPS. In AWS D1.1:2025 the minimum comes from Table 5.11, Prequalified Minimum Preheat and Interpass Temperature, and clause 5.7.1 makes it mandatory for the steels the code lists. Reading it takes four decisions: the category, the governing thickness, the mixed-joint rule, and whether the table applies to your steel at all.

Rule library based on AWS D1.1:2025; verify against your governing edition (the AHJ or contract may specify an earlier one).

Step 1: Find the Category

Table 5.11 does not group steels by strength alone. Each category is a combination of steel specifications and welding processes. The common structural cases:

Category Typical steels Process ≤ 3/4 in Over 3/4 thru 1-1/2 in Over 1-1/2 thru 2-1/2 in Over 2-1/2 in
A A36, A500 Gr B/C, A53 Gr B, A709 Gr 36 SMAW with other than low-hydrogen electrodes 32 °F 150 °F 225 °F 300 °F
B A36, A500 Gr B/C, A572 Gr 42/50/55, A588, A709 Gr 36/50, A992, A913 Gr 50 Low-hydrogen SMAW, SAW, GMAW, FCAW 32 °F 50 °F 150 °F 225 °F
C A572 Gr 60/65, A709 HPS70W, A913 Gr 70 Low-hydrogen SMAW, SAW, GMAW, FCAW 50 °F 150 °F 225 °F 300 °F

Two further categories cover specific steels welded with H8 consumables: Category D (for example A913 Grades 50, 60 and 65, 32 °F at all thicknesses) and Category E (A1066 Grades 50, 60 and 65, 50 °F up to 1 in and 120 °F over 1 in). Check the full table for any steel not shown here.

The same A36 plate lands in Category A with E6010 and Category B with E7018. That is why the process belongs on the preheat line of the WPS, not just the steel.

Cold base metal. Table note a: when the base metal is below 32 °F, preheat it to at least 70 °F and keep that as the minimum interpass temperature, even where the table value is 32 °F.

Step 2: Measure the Governing Thickness

The table column is the thickness of the thickest part at the point of welding. For a T-joint between a 3/8 in stiffener and a 1-1/2 in flange, the flange sets the row. For a repair on heavy plate, use the plate being repaired, not the size of the excavation.

This is the opposite of minimum fillet weld size, where low-hydrogen processes use the thinner part joined. Mixing those two rules up is a common WPS review finding. See heat-affected zone control in WPS development for why thickness drives cooling rate.

Step 3: Apply the Mixed-Joint Rule

Clause 5.7.2 covers joints between base metals that would get different minimums: use the highest. An A36 web welded to an A572 Grade 65 flange is not Category B. The Grade 65 flange is Category C, so the joint takes the Category C value for the governing thickness.

Step 4: Check Whether Table 5.11 Applies at All

Table 5.11 covers the steels listed in it. When a steel is not listed (pipe piling to ASTM A252 and anchor rods to ASTM F1554 are common examples), or when restraint, hydrogen level or chemistry make the table value questionable, the code points to Annex B, Guideline on Alternative Methods for Determining Preheat. Annex B is where carbon equivalent, hydrogen level and hardness control come in. See carbon equivalent and preheat under AWS D1.1 and hydrogen cracking prevention in WPS documentation.

Clause 5.7.3 also allows alternate preheat for parallel or multiple electrode SAW, with the Engineer's approval for single-pass welds.

Documenting Preheat on the WPS

The preheat section of the WPS should state actual values, not "per code":

  1. Minimum preheat: the Table 5.11 value for the governing category and thickness, or higher if the PQR, Annex B or the project specification requires it
  2. Minimum interpass temperature: at least the preheat minimum
  3. Maximum interpass temperature: required where the base metal or the contract limits it, for example quenched and tempered steels
  4. Heating method: torch, induction or resistance blankets

A WPS that only says "preheat per AWS D1.1" is not wrong, but it is incomplete and tends to fail third-party audits. Interpass control is covered in interpass temperature control for CWIs.

CWI Verification Sequence

Before the first arc:

  1. Confirm the heat number matches the MTR and that the steel is listed in Table 5.11.
  2. Confirm the process and electrode, since they decide the category.
  3. Measure the thickest part at the point of welding to pick the row.
  4. Apply clause 5.7.2 if the joint mixes categories.
  5. Measure the temperature with a calibrated method; see preheat temperature measurement methods.

If welding started below the minimum, document it as a nonconformance. It does not automatically require removing the weld, but it does require an engineering evaluation.

Common Mistakes

Mistake Prevention
Citing the wrong table number In D1.1:2025 preheat is Table 5.11
Using the thinner part's thickness Preheat uses the thickest part at the point of welding
Ignoring the process E6010 (Category A) and E7018 (Category B) give different values on the same steel
Applying one category to a mixed joint Clause 5.7.2: use the highest minimum
Using Table 5.11 for unlisted steels Use Annex B or a qualified procedure
Forgetting the cold-weather rule Below 32 °F base metal, preheat to at least 70 °F

Summary

Read Table 5.11 as category (steel plus process), then the thickest part at the point of welding, then clause 5.7.2 when two steels meet, then Annex B when the steel or the conditions fall outside the table. Software that fills these values from the WPS inputs removes the most common lookup errors; see pricing for how wps-welding handles it.

FAQ

Frequently asked.

Which table in AWS D1.1:2025 gives minimum preheat?
Table 5.11, Prequalified Minimum Preheat and Interpass Temperature. Clause 5.7.1 requires it to be used for the steels listed in the code. Some older articles and shop forms cite other table numbers carried over from earlier editions; in the 2025 edition the table is 5.11. Table 6.3 in D1.1:2025 covers PJP groove test specimens, not preheat.
Does Table 5.11 have separate columns for high and low heat input?
No. Table 5.11 is organized by category (steel specification plus welding process) and by the thickness of the thickest part at the point of welding. Heat input and carbon equivalent are not inputs to Table 5.11. Carbon-equivalent and hardness-based preheat methods are in Annex B, Guideline on Alternative Methods for Determining Preheat.
What preheat does A572 Grade 50 need with E7018?
A572 Grade 50 welded with low-hydrogen SMAW, SAW, GMAW or FCAW is Category B: 32 °F up to 3/4 in, 50 °F over 3/4 through 1-1/2 in, 150 °F over 1-1/2 through 2-1/2 in, and 225 °F over 2-1/2 in, based on the thickest part at the point of welding. Below 32 °F base metal temperature, preheat to at least 70 °F. Rule library based on AWS D1.1:2025; verify against your governing edition.
What if the two parts of a joint need different preheats?
Clause 5.7.2: when a joint combines base metals with different minimum preheats from Table 5.11, based on category and thickness, apply the highest of those minimums.

More from the blog