WPS Requirements for Solar Ground Mount Structural Steel
Ground-mount solar racking is structural steel. AWS D1.1 governs the welds — here is what WPS qualification, fillet sizing, and CWI inspection mean for PV projects.
Utility-scale solar construction has scaled into one of the largest structural steel market segments in the country, and much of it is welded. Ground-mount photovoltaic (PV) arrays use driven or helical steel posts, horizontal purlins, torque tubes, and racking cross-members — all structural steel that must transfer wind, gravity, and seismic loads to the foundations. When those steel members are welded in fabrication or in the field, the welds are structural welds, and AWS D1.1 is the governing code.
For CWI inspectors, QC managers, and EPC subcontractors who are encountering solar racking welding for the first time, the requirements are not exotic — they are the same AWS D1.1 framework that governs any structural steel project. What is different is understanding which WPS procedures are needed, how the typical joint configurations fit into prequalified status, and what the special challenges of field-welded racking installation look like.
Which Structural Members Are Welded
Not all solar racking connections are welded. Many utility-scale racking systems are bolted at the top chord connections, with the main structural posts driven directly into the ground. However, welded connections are common in several locations:
Fabricated torque tube assemblies — rolled tubes with welded end flanges for mechanical drive attachment
Racking main beams to column cap plates — fillet welds connecting the horizontal bearing member to a shop-welded cap plate on the vertical post
Field-welded splice connections — when racking sections are too long for delivery and must be spliced on site
Equipment pad support structures — welded steel frames supporting inverters, transformers, and switchgear within the solar array
Ground-mounted perimeter fence and access road support structures — structural steel welded at AISC fabricators for the site infrastructure
The electrical mounting hardware (module clamps, wire management clips) is not structural welding and AWS D1.1 does not apply to it.
Code Jurisdiction and Contract Requirements
AWS D1.1 applies when the welded base metal is structural steel, 1/8 in [3 mm] or thicker, and the welds are load-carrying. Most utility-scale solar EPC contracts include a specification section that invokes AWS D1.1 for all structural welding. Some state building departments with jurisdiction over large solar installations also reference AWS D1.1 through the IBC for the inverter pad structures and perimeter building components.
If you are a subcontractor welding torque tube assemblies or racking sections in a shop, your customer's quality requirements will typically specify:
Applicable welding code (AWS D1.1:2025 or the edition the EPC specifies)
Welding process restrictions (FCAW-G and GMAW are common for shop fabrication; SMAW may be required for field welding in wind-exposed conditions)
NDE requirements (visual inspection at minimum; MT or PT spot-check at specified sampling rates for critical connections)
WPS and WPQ documentation to submit with the fabrication package
Rule library based on AWS D1.1:2025; verify against your governing edition.
WPS Qualification Approach for Solar Racking
Most solar racking welded connections are fillet welds or partial joint penetration (PJP) groove welds on base metals listed in AWS D1.1:2025 Table 5.6. This means they are eligible for prequalified WPS qualification under Clause 5, which does not require a PQR qualification weld.
Typical base metals encountered in solar racking fabrication:
A500 Grade B/C HSS — round and rectangular tubes for posts and purlins, listed in Table 5.6 Group II
A1085 HSS — newer specification with tighter wall thickness tolerances, also listed in Table 5.6
A36 plate and angle — cap plates, gussets, and base plate components
A992 wide flange — heavier support columns for inverter pad structures
Fillet welds connecting these materials are prequalified under AWS D1.1:2025 Clause 5 when:
The joint geometry matches a prequalified configuration (flat, horizontal, or vertical for FCAW-G or GMAW)
The filler metal is from the prequalified list for the process (E71T-1, ER70S-6, E7018, etc.)
Preheat meets the minimum requirements for the base metal thickness and specification
For shops already doing structural fabrication, adding solar racking to the production scope does not necessarily require new PQR testing — your existing WPS procedures for FCAW-G or GMAW on A500 HSS fillet welds likely already cover the work.
Minimum Fillet Weld Size
AWS D1.1:2025 Table 7.7 gives the minimum fillet weld size based on the thickness of the thinner part at the joint. For low-hydrogen processes (FCAW-G, GMAW, SMAW E7018), the minimum fillet weld size for common HSS wall thicknesses is:
Thinner part ≤ 1/4 in [6 mm]: minimum 1/8 in [3 mm] fillet weld
Thinner part over 1/4 in through 1/2 in [6 to 12 mm]: minimum 3/16 in [5 mm]
Thinner part over 1/2 in through 3/4 in [12 to 20 mm]: minimum 1/4 in [6 mm]
Standard A500 HSS sections used in solar racking typically have wall thicknesses in the 1/4 in to 3/8 in range, putting the minimum fillet weld at 3/16 in. The engineer's drawings will specify the actual required fillet weld size based on the structural demand, which is often larger than the minimum.
For thin-wall HSS (under 3/16 in wall thickness), which appears in some light-duty racking systems, special care is needed. Single-pass fillet welds on thin wall HSS require WPS parameters that control heat input to prevent burn-through. See thin-wall HSS burn-through WPS controls under AWS D1.1 for guidance.
Welder Qualification for Solar Racking
Welders performing structural racking welds must hold a valid WPQ (welder performance qualification) under AWS D1.1 for the applicable process, position, and thickness range. For shop fabrication of racking sections in the flat and horizontal positions, a standard FCAW-G or GMAW WPQ covering 1F/2F/1G/2G positions is sufficient.
For field welding of racking splice connections or cap plate joints in vertical or overhead positions, the WPQ must cover those positions (3F/4F/3G/4G as applicable). If your shop WPS procedures are written for flat and horizontal only, field welders performing out-of-position welds will need either a separate WPS for those positions or a groove weld WPQ that covers all positions by virtue of a 3G or 4G test.
Welder continuity requirements under AWS D1.1 Clause 6.4.1 apply to solar racking welding just as they do to building structural welds. Welders who have not performed work under AWS D1.1 within the past six months must requalify. For shops running seasonal solar construction crews, tracking welder continuity is a real compliance concern — the AWS D1.1 welder continuity tracker tool can automate the alert workflow.
Field Welding Challenges
Utility-scale solar arrays are built in open fields with significant wind exposure, which creates three recurring problems for field welders:
Wind affecting shielding gas. FCAW-G and GMAW shielding gas is disrupted by wind above approximately 5 mph at the weld point. AWS D1.1 requires protection from wind when gas-shielded processes are used. Field welding crews must use portable wind barriers or switch to self-shielded FCAW-S or SMAW in exposed conditions. Your WPS must cover the actual process being used in the field — a shop WPS for FCAW-G is not applicable for FCAW-S field welding.
Preheat in cold weather. Thin HSS in cold weather meets the minimum preheat thresholds for Group II materials even at moderate temperatures. At ambient temperatures below 32°F [0°C], AWS D1.1 requires preheat regardless of thickness. Field welders on solar projects in cold climates need propane preheat torches and pyrometers, and the WPS must specify the minimum preheat.
Base metal surface condition. Drive posts and in-ground steel arrive with mill scale, light rust, and sometimes protective coatings. AWS D1.1 Clause 5.6 requires that weld areas be clean and free of materials that would adversely affect weld quality. For solar field welds, a weld area prep step (wire brushing or grinding at the joint) should be part of the written work procedure.
Inspection and Documentation Package
For utility-scale solar projects, the typical inspection and documentation package for structural welds includes:
WPS procedures for each process and joint configuration, with copies submitted to the EPC QC representative
WPQ records for each welder, certified within the past 12 months or with continuity documentation showing no six-month lapse
Visual inspection records for all structural welds with accept/reject status per AWS D1.1 visual acceptance criteria in Clause 9
NDE records for any spot-check MT or PT required by the project specification
Welder ID traceability connecting each weld to the qualified welder who made it, as required by the project QC plan
Maintaining this documentation across a utility-scale solar project with hundreds of discrete welded connections requires a systematic approach. For shops building racking in quantity, digital WPS and WPQ management eliminates the paper chase and gives EPC customers a complete, audit-ready documentation package at project closeout.
Does AWS D1.1 apply to solar ground mount racking structures?
When the racking uses structural steel (HSS, wide flange, angle, channel) of 1/8 in [3 mm] or greater thickness and the welds carry structural loads, AWS D1.1 applies. The engineer of record for the racking system specifies the governing code. Many utility-scale EPC contracts explicitly call for AWS D1.1 compliance on all structural welds.
Can prequalified WPS procedures be used for solar racking connections?
Yes, if the base metal is listed in AWS D1.1:2025 Table 5.6 and the joint details match a prequalified configuration under Clause 5. Most HSS tube-to-tube and tube-to-plate fillet weld connections used in ground-mount racking qualify for prequalified WPS status, eliminating the need for a PQR.
What fillet weld sizes are typical for solar racking connections?
Racking connections typically use 3/16 in to 5/16 in fillet welds depending on the tube wall thickness. The minimum fillet weld size is set by AWS D1.1:2025 Table 7.7, using the thinner part at the joint as the governing thickness for low-hydrogen processes.
Do welder qualifications (WPQ) transfer between solar project sites?
Yes. A WPQ issued under AWS D1.1 is not project-specific. A welder qualified for FCAW-G on flat and horizontal positions can perform that work on any AWS D1.1 project without requalifying, as long as the essential variables of the WPS fall within the qualified ranges.