When a new structural project comes in and the project manager asks "when can we start welding?" the answer is not just "when the WPS is qualified." It is also "when the WPS submittal has been reviewed and returned by the engineer of record, if the contract requires that." Understanding what drives that review — and what AISC 303 says about it — keeps shops from scheduling conflicts that delay fabrication starts.
AWS D1.1:2025 is the welding code. AISC 303 is the contracting framework. Both are in play on most commercial structural steel projects, and they address different things. Knowing where one ends and the other begins prevents both missed submittal obligations and unnecessary hold-ups.
Rule library based on AWS D1.1:2025; verify against your governing edition.
What AISC 303 covers
The AISC Code of Standard Practice (AISC 303) establishes the standard customs and practices of the structural steel industry — what fabricators and erectors do by default when contracts are silent on a particular point, and what the parties' respective obligations are across the project lifecycle.
Section 4 of AISC 303 addresses submittals, defining the fabricator's obligation to submit shop drawings, erection drawings, and other required documents for review. While AISC 303 does not enumerate WPS as a specific submittal type the way it does shop drawings, project specifications that invoke AISC 303 frequently list WPS submittals in the submittal schedule.
Section 6 covers fabrication. AISC 303 requires that fabrication be performed in accordance with the contract documents, including applicable welding codes. The practical effect is that AISC 303 tells the parties how the contract runs; AWS D1.1 tells the welder how the weld is made.
For AISC 360-governed projects, the structural specifications often include a section on quality assurance that directly references both AISC 303 and AWS D1.1. See AISC 360 structural weld QC and AWS D1.1 for how the two documents overlap on quality program requirements.
The submittal obligation
On most commercial structural steel projects, the contract specification includes a submittal schedule — a list of documents the fabricator must submit, to whom, and when. WPS submittals appear on this list with their own action code (typically "review required" or "approval required") and a required submission date relative to the start of fabrication.
Required versus informational submittals: Some specifications treat WPS submittals as informational only — submit and proceed. Others require explicit engineer acceptance before welding begins. The distinction has scheduling consequences. A shop that submits WPS the day before planned arc strike and the contract requires EOR approval before welding has a problem.
What goes in the WPS submittal: A complete WPS submittal package typically includes:
- All WPS documents to be used on the project, including prequalified WPS and tested WPS
- PQR summaries for tested WPS (some engineers require the full PQR; others accept a WPS that cites the PQR number)
- A WPS index cross-referencing weld types, positions, and member categories to WPS numbers
- Welder qualification summary table for key welders, or a statement that WPQ records will be available on request
Prequalified WPS: Fabricators sometimes assume that prequalified WPS under AWS D1.1:2025 Clause 5 do not require submittal because they are inherently code-compliant. This is incorrect. Prequalified WPS still require documentation, still require a CWI signature, and still appear on the submittal schedule. They are "prequalified" in the sense that they do not require a test coupon and PQR — they are not exempt from contract submittal requirements.
What the EOR review covers
When an engineer stamps a WPS submittal, the scope of that review depends on what the contract requires and what the engineer chooses to do. In practice, structural engineers reviewing WPS submittals are checking:
Code compliance on face value: Does the WPS identify a process, base metal group, filler metal, position, and preheat range? Is it signed and dated? Does it appear to follow the format required by AWS D1.1?
Project applicability: Are the base metals on the submittal consistent with the materials specified on the structural drawings? Do the processes and positions match what the shop drawings show?
CVN requirements: If the contract specifies supplementary essential variables (CVN toughness requirements for demand-critical welds or low-temperature service), has the WPS addressed them? See CVN supplementary essential variables under AWS D1.1:2025 Table 6.8.
What the EOR review does not cover: Most structural engineers do not have the welding expertise or the time to independently verify that a tested WPS is properly supported by its PQR, that the preheat values are correct for the specific carbon equivalent of the specified steel, or that the essential variables in Table 6.6 are fully addressed. The fabricator cannot rely on an EOR approval stamp as confirmation that the WPS is technically correct — that responsibility stays with the CWI and QC manager.