When a prime fabricator or general contractor subcontracts structural welding work, two welding procedure documents arrive on the same job site: the prime's QC plan and the sub's welding procedures. The sub brings their own WPS and PQRs, their own welders, and often their own inspection setup. The prime CWI is responsible for verifying that what the sub brought actually meets the project specification — and that responsibility doesn't disappear just because the sub has a thick folder of paper.
Failures here are not hypothetical. Third-party audits and owner inspections routinely flag projects where a sub's WPS was accepted without verification, only to reveal that the procedure didn't cover the joint thickness actually being welded, cited the wrong edition of D1.1, or had a PQR with mechanical test results that didn't meet current acceptance criteria.
Who is responsible for what
AWS D1.1 places the qualification obligation on the contractor or fabricator doing the work. The sub, as the party making the welds, is responsible for having a compliant WPS and qualified welders. But the prime contractor is responsible for the work scope they contracted out — which means they cannot accept the sub's work without verifying the sub's documents.
The structural drawings and project specification define which edition of D1.1 governs. The prime CWI must confirm that the sub's WPS and PQRs comply with that edition. If the project specifies AWS D1.1:2025 and the sub submits procedures written to the 2020 edition, the CWI must evaluate whether the procedures meet 2025 requirements — not simply whether they comply with their stated edition. Several technical rules changed between editions, including Table numbering for essential variables and specific row-level requirements in what is now Table 6.6. See AWS D1.1:2025 vs 2020: what changed for a focused diff.
The responsibility question for WPS authorship — who writes it, who stamps it — is separate from who performs the work. See WPS responsibility: fabricator, contractor, and EOR for the general framework.
The document package to request from a sub
Before a sub's crew starts making structural welds, request and review:
1. WPS for each process and joint type The sub should provide a WPS for every welding process and joint configuration they will use. A sub doing SMAW on groove joints and FCAW-G on fillet welds needs two procedures — one for each process — unless a single WPS explicitly covers both. The WPS must specify process, filler metal, base metal group, position(s), preheat requirements, and all other essential variables per AWS D1.1 Table 6.6.
2. Supporting PQR(s) for each WPS Every WPS must be backed by at least one PQR — unless it is a prequalified WPS meeting all conditions of Clause 4 of AWS D1.1. For each PQR, verify:
- Mechanical test results (tensile, bend) meet D1.1 acceptance criteria
- The test was witnessed by a CWI (name and signature on the PQR)
- The base metal and filler metal tested are consistent with what the WPS specifies for the project
- Thickness and position of the test coupon support the production parameters
For more on reading a PQR test report, see how to read a PQR test report.
3. Current WPQ or WOPQ records for all welders/operators Request a qualified welder list with current WPQ records for every person the sub intends to deploy. Confirm:
- Each WPQ covers the process and position(s) the welder will use in production
- The continuity record shows the welder has used the process within the prior 6 months (AWS D1.1 Clause 6.4.1)
- The WPQ is signed by a CWI
A common gap is a sub who provides a welder list but not the underlying WPQ forms. The list is not a qualification record — the signed, witnessed WPQ is the record.
4. Quality plan or inspection and test plan (if required by spec) Some owner specifications and AISC-certified shop requirements require the sub to submit a quality plan describing their internal inspection process. At minimum, understand who on the sub's crew is responsible for visual inspection and NDE witness, and whether they have a CWI.