Procedure qualification has a reputation for being slow and expensive. Done badly, it is. Done well, the timeline is 2–3 weeks and the cost is a few thousand dollars. Here is the sequence experienced welding engineers use.

Step 1 — write the draft WPS first

Before any test weld, the parameters must be on paper. The draft WPS specifies:

  • Process, filler classification, base metal specification
  • Joint detail with sketch
  • Position
  • Amperage, voltage, travel speed (specific values for the coupon; the WPS will later expand to ranges)
  • Preheat, interpass
  • CVN requirement (yes or no — this drives lab specimen geometry)

Without a draft WPS, the test weld has nothing to validate.

Step 2 — pick the test coupon

For groove welds, the standard coupon is a plate or pipe in the position you want to qualify, thick enough to span the thickness range you want to support. AWS D1.1 Clause 6 specifies coupon sizes.

A common practical choice: 1-inch-thick plate for groove welds, qualifying down to 1/8-in plate and up to 2x the coupon thickness (so 2 inches on the upper end).

For fillet welds, the standard is a T-joint coupon with the larger leg on top.

Step 3 — schedule the welder, the inspector, and the lab

This is the step shops underestimate. Three calendars have to align:

  • Welder — must be currently WPQ-qualified in the process
  • CWI (in-house or contracted) — to witness and record
  • Lab — accredited per A2LA, IAS, or NVLAP; book the slot before welding the coupon

Lab capacity is usually the bottleneck. If you weld on a Monday and discover the lab can't take your coupon for three weeks, you've added three weeks for no reason.

Step 4 — weld the coupon

The CWI:

  • Verifies the welder's stamp and current WPQ
  • Confirms base metal mill cert and filler lot number
  • Records pre-weld surface condition, joint fit-up, preheat
  • Records every parameter at the coupon, every pass: amperage, voltage, travel speed, interpass temperature
  • Marks the coupon with a unique ID, ties it to the PQR number

This data goes onto the PQR before the coupon leaves the floor.

Step 5 — ship and test

The coupon goes to the lab with a sealed test request that specifies:

  • Code and edition (AWS D1.1:2025)
  • Tests required: tensile (typically 2 specimens), bend (face + root or side bends), CVN if required
  • Acceptance criteria from the code
  • PQR number for the lab report

A good lab returns results in 5–10 business days.

Step 6 — compile and sign the PQR

The PQR consolidates:

  • The welded coupon data (parameters, witnessing)
  • The lab report (tensile, bend, CVN results)
  • A pass/fail determination per the code's acceptance criteria
  • Signature of the welding engineer or CWI

The PQR is then filed permanently. From this point, you can write one or more WPSs that cite it.

Step 7 — write the production WPSs

From a single PQR, you can write WPSs that:

  • Expand the recorded amperage / voltage / travel speed to ranges allowed by Table 6.6
  • Cover additional positions if the test position qualifies them per Clause 6 position tables
  • Cover thinner and thicker plate up to the qualified thickness range
  • Support fillet welds if the groove test qualifies fillets per Clause 6

Each WPS cites the supporting PQR by number.

Cost and timeline summary

  • Welder time + inspector time: $300–$1,500
  • Lab tests: $800–$2,500
  • Total: $1,500–$4,000
  • Calendar: 2–4 weeks if the lab is responsive

A failed coupon adds the cost of one full cycle. A second-time pass with a tightened draft WPS is the norm.