Discovering a rejectable discontinuity after NDE is a stressful moment on any job site — but the response procedure matters as much as the repair itself. AWS D1.1:2025 has specific requirements governing how repair welds are qualified, documented, and inspected. Getting those requirements wrong can turn a routine repair into a nonconformance that fails a third-party audit or a contractor QC review.
The most important principle: a repair weld is still a weld. It must be covered by a valid WPS, performed by a qualified welder, and reinspected to the same NDE requirements as the original weld.
Rule library based on AWS D1.1:2025; verify against your governing edition.
When the existing WPS still applies
In most repair scenarios, the original WPS is still the governing procedure. If you are:
- Excavating a porosity cluster or incomplete fusion indication to sound metal using air-carbon arc gouging or grinding
- Re-welding the excavated area with the same filler metal, same process, same polarity, and within the same preheat and interpass temperature range that the original WPS specifies
- Returning the weld to the same cross-sectional dimensions as the original joint design
...then no new qualification is required. The existing WPS already covers those essential variables.
The repair is documented as a repair event in the quality records, not as a new WPS qualification. What you need is:
- The identity of the original weld (weld ID, drawing reference, location)
- The nature of the rejectable indication and the NDE report that triggered the repair
- The excavation method and verified removal of the defective area
- The WPS used for re-welding (cite the existing WPS number)
- The post-repair NDE result and the inspector release signature
When requalification IS triggered
The repair situation forces a process or essential-variable change more often than people expect. Common scenarios that require additional qualification:
Switching to GTAW for root access. A tight joint was originally welded with FCAW. The defect is at the root. The repair requires GTAW because the gun won't reach into the excavated area. GTAW and FCAW are different processes — a FCAW PQR does not support a GTAW WPS. The repair requires a GTAW PQR or a pre-existing GTAW WPS with its own PQR support.
Changing filler metal to control heat input. The original weld was run with a higher-heat-input process. The repair on a distortion-sensitive section calls for a lower-heat-input process or a different electrode classification. Any change in filler classification is an essential variable change under Table 6.6 requiring PQR support.
Repair on a different base metal. Occasionally, a repair situation reveals that the base metal delivered is different from what the WPS covers — a material verification failure discovered late. The repair WPS must be qualified for the actual base metal in the structure, not just the specified base metal.
CVN-required work. If the original weld was in a demand-critical application requiring CVN toughness under Table 6.8, the repair weld is subject to the same CVN supplementary essential variable controls. A process change or heat-input change that wouldn't matter on a non-CVN weld can trigger requalification when Table 6.8 applies. See CVN supplementary essential variables under AWS D1.1:2025 for what Table 6.8 specifically controls.
Seismic demand-critical connections. For AWS D1.8 seismic supplement applications, repair weld requirements are more stringent. The repair filler metal, process, and inspection requirements follow the demand-critical provisions, not general D1.1 fabrication provisions. These must be explicitly addressed in the project ITP (Inspection and Test Plan).
Excavation method and pre-repair NDE
AWS D1.1 requires that the defect be fully removed before re-welding. The two common excavation methods are:
Air-carbon arc gouging (CAG). Fast and effective for removing large volumes of weld metal. Leaves a heavily carburized surface that must be ground before welding. The grinding requirement is mandatory — CAG alone does not prepare a surface for re-welding. The carburized zone will harden on cooling and create a hydrogen cracking risk if not removed.
Grinding. Slower but produces a clean surface directly. Preferred for precision excavation of small defects, root pass conditions, or situations where the adjacent base metal cannot tolerate the thermal shock of arc gouging.
After excavation and before re-welding, the cavity must be inspected — typically by MT or PT — to confirm complete removal of the indication. This is the pre-repair NDE step. Skipping it and simply filling the cavity is the most common repair procedure violation found in CWI audits.
See magnetic particle testing documentation under AWS D1.1 for the acceptance criteria and documentation requirements for the pre-repair MT inspection.
Preheat for repair welds
Preheat for a repair weld is at least as important as preheat for the original weld — often more so. The reasons:
- The base metal adjacent to the repair area has already been through one thermal cycle. The heat-affected zone from the original weld may have higher hardness than virgin base metal.
- Hydrogen cracking risk is elevated on repair welds because the weld is surrounded by previously deposited metal with existing residual stresses.
- If the excavation involved air-carbon arc gouging, the thermal cycle from gouging has further altered the HAZ microstructure.
AWS D1.1 does not specify a separate preheat table for repair welds — the same carbon equivalent-based preheat tables apply. However, many experienced CWI inspectors and QC managers require preheat for repair welds even when the carbon equivalent calculation technically allows welding without it, especially on higher-carbon base metals or heavy sections.
When in doubt, apply preheat. A failed charpy test or a hydrogen crack on a repaired critical weld is far more expensive than the time and propane required for adequate preheat.
Documenting the repair in the quality record
The repair weld needs its own quality record, distinct from the original weld record but linked to it by weld ID. That record must show:
- Original weld ID and location — which weld was repaired, on which drawing revision
- NDE report that triggered the repair — the original rejection, with indication type, size, and location
- Excavation method — CAG, grinding, or both; who performed it and when
- Pre-repair NDE — method, result, and inspector release (confirming full removal of indication)
- Repair WPS — by WPS number; if a different process is used, cite the separate WPS and confirm PQR support
- Welder ID — who performed the repair, with WPQ qualification confirmed
- Post-repair NDE — full re-inspection to the same method and extent as the original weld
- Inspector release — CWI or authorized inspector sign-off on the completed repair
Some contract specifications and project quality plans require the fabricator to notify the EOR (Engineer of Record) or the project owner's QC representative before proceeding with repair of certain critical joints. Check the project-specific ITP before starting any repair on primary structural members.
Repair limits and second repair provisions
AWS D1.1 does not prohibit multiple repair attempts on the same weld, but quality plans and contract specifications sometimes do. Some Tier 1 structural contractors limit repairs to one attempt on demand-critical joints; a weld that fails post-repair NDE may require the entire joint to be removed and requalified.
Even under general D1.1 provisions, repeated repair attempts on the same location raise real metallurgical concerns:
- Accumulated heat input degrades HAZ microstructure
- Residual stress buildup increases hydrogen cracking risk
- Carbon migration from repeated CAG cycles can contaminate the weld area
If a weld fails a second post-repair NDE, bring the CWI, the QC manager, and the EOR into the decision before attempting a third repair. Document that discussion.
Welder qualification for repairs
The welder performing the repair must hold a valid WPQ for the process, position, and material used in the repair — not just the process used in the original weld. This catches a common planning error: the only available welder on site is qualified for SMAW in the flat and horizontal positions, but the repair joint is in the overhead position. That welder cannot perform the repair without either getting the joint repositioned or bringing in a welder qualified for overhead.
For welder continuity purposes, repairs performed by welders whose WPQ is within its active period count as valid production weld work, maintaining continuity under AWS D1.1 Clause 6.4.1. A repair does not reset the clock. See welder continuity tracking under AWS D1.1 for how the six-month continuity requirement works.
Repair welds in an audit-ready QC system
The quality record trail for repair welds is one of the areas most commonly flagged in AISC certification audits and owner QC reviews. The specific weaknesses are:
- Pre-repair NDE not documented (or not performed)
- Repair WPS not cited in the record (just "same as original")
- Post-repair NDE type changed (from RT to UT) without documented justification
- Welder ID missing on the repair record
Building repair documentation into your standard WPS management workflow — with a repair weld template linked to the original weld record — prevents these gaps from accumulating. See welding procedure library setup for audit-ready fab shops for how to structure production quality records.
Shops using a software-based WPS management system can track repair events directly against weld IDs, maintain the pre- and post-repair NDE results in the same system, and generate the complete repair audit trail on demand. See the pricing page for how the platform handles repair documentation alongside standard WPS and PQR management.