A plate girder shop-fabricated under controlled conditions. The same girder arrives on site and an erection crew makes the field splice CJP groove welds. Who is responsible for the WPS? Who provides the CWI? If the erector's welder is qualified under a different organization's WPQ records, are those valid under the project specification?
These questions come up on nearly every multi-trade structural steel project, and the answers are not found in AWS D1.1 alone. The standard tells you the technical requirements for every weld—qualification testing, essential variables, documentation. The AISC Code of Standard Practice (COSP) tells you which party in the contract is responsible for which scope of work, including welding.
The AISC COSP Division Between Fabricator and Erector
The AISC Code of Standard Practice for Steel Buildings and Bridges draws a contractual boundary between the fabricator (who produces structural members in the shop) and the erector (who assembles and connects them at the jobsite). These can be the same company or different companies, depending on the procurement structure.
When fabrication and erection are split between separate entities—a fabricator who ships steel and a specialty erector who bolts and welds connections—the erector is not automatically covered by the fabricator's WPS package, quality manual, or inspection program. The erector is an independent contractor responsible for the quality of their own work.
This matters for WPS because a field-bolted connection requires no WPS, but a field-welded connection does. Any field welding—beam-to-column CJP moment connections, field splice welds, flange plate attachments, column splice welds—requires:
- A qualified WPS covering the joint type, process, position, and base metals
- Welders qualified under that WPS (valid WPQ records)
- CWI inspection per the project specification and governing code
If the erector is doing the welding, the erector must either have their own WPS documentation or obtain it from the fabricator by explicit contract arrangement. Assuming the fabricator's WPS covers the erector's field welding scope without that written arrangement is a common project-start error.
How the Project Specification Governs the Split
The project specification—typically written by the EOR referencing AISC 303 (Standard Practice), AISC Chapter N (QC/QA), and AWS D1.1—is the document that allocates welding responsibility between parties. Specifications vary widely in how explicit they are:
Explicit scope allocation: Some specifications state that all field welds are performed by the erector under the erector's welding program, with the erector providing their own WPS, welder qualification records, and field CWI.
Fabricator-scope-only language: Other specifications are written entirely around the fabricator's shop program without addressing erection welding explicitly. In these cases, the EOR may assume the fabricator is doing both shop and field work, which creates a gap if a separate erector is procured later.
Single-entity assumption: Many smaller projects use a single steel contractor who fabricates and erects. Here the WPS library applies to both shop and field operations, but the procedures must still cover field joint configurations and positions. Shop qualification of flat-position (1G, 1F) groove and fillet welds does not cover overhead (4G, 4F) field welds.
The practical takeaway: before steel erection begins, the QC manager should confirm in writing which party holds responsibility for each weld type in the field. Do not assume.
WPS Position Coverage in the Field
Even when a single company performs both fabrication and field erection under one WPS library, the field presents positions that may not be covered by the shop WPS qualification.
A typical shop WPS for flat-position groove welding (1G) qualifies the welder in 1G and 2G (horizontal) per AWS D1.1 position qualification rules. Overhead (4G) and vertical (3G) positions require separate qualification. Field conditions regularly require overhead and vertical welding—column splices made in the vertical position, flange welds made in overhead position under beam flanges, beam-to-column CJP welds made in the horizontal or vertical position depending on the connection geometry.
CWIs reviewing field welding programs should verify that every position used in the field is covered by the WPS and by the individual welders' WPQ records. A welder who is qualified only in 1G attempting a 4G field weld is a non-conformance waiting to happen.
The welding position qualification limits under AWS D1.1 article covers the qualification position coverage tables in detail. For field welding planning, cross-reference the WPS position list against the actual joint orientations in the erection drawings.