A WPS authorizes a procedure. A WPQ (Welder Performance Qualification) authorizes a welder to follow it. The link between the two is the most-audited connection in welding QC. Auditors walk the production floor, identify a weld, and trace it both upward to a WPS and sideways to the welder's WPQ. Any break in either trace is a finding.
What a WPQ contains
A complete AWS D1.1 WPQ records:
- Welder's name, employee ID, and stamp number
- Date of qualification test
- WPS used for the test (or the qualifying parameters)
- Process(es) tested
- Position(s) tested
- Thickness range qualified (derived from test thickness)
- Diameter range qualified (for pipe)
- Test results — typically visual + bend tests per Clause 6
- Witnessing inspector's name, credential, and signature
- Continuity record start date
A WPQ is signed by the witnessing CWI or inspector.
Position tables — what a WPQ actually qualifies
AWS D1.1 Clause 6 includes position tables that map test positions to qualified production positions. A few common rules:
- 1G test (flat groove) qualifies 1G and 1F production only
- 2G test (horizontal groove) qualifies 2G + 1G + 1F + 2F
- 3G test (vertical groove) qualifies 3G + 2G + 1G + 1F + 2F + 3F
- 3G + 4G tests together qualify all positions (3G + 4G = full position qualification)
- 6G test (45° fixed pipe) qualifies all positions for both pipe and plate
The full position picture comes from 3G + 4G or 6G. Most production shops have welders qualified to one of those two combinations.
Thickness range
Test thickness sets the qualified production thickness range:
- Test on 3/8 in → qualified for 1/8 in to 3/4 in production (roughly)
- Test on 1 in → qualified for 1/8 in to unlimited
- Test on pipe at 6 in NPS schedule 80 → qualified for that diameter and most smaller diameters
The exact qualified range comes from Clause 6 thickness tables. A rule engine that knows the tables can output "Welder X is qualified for WPS Y" or "not qualified" deterministically.
Continuity — the 6-month rule
Once qualified, a welder maintains qualification by using the process at least once every 6 months. Documentation requirements:
- Continuity log shows welder's name, process, and date of last production weld
- Foreman or QC clerk updates after each production cycle
- If a welder lapses on a process, their WPQ for that process is suspended until requalification
The continuity log is a common audit finding. Shops with a paper log update it sporadically; the auditor walks in mid-month and the log is 6 weeks out of date.
How to enforce traceability
Three approaches:
1. Paper assignment slips. Each weld assignment has a slip listing the WPS, the welder, the welder's WPQ. Inspector verifies before welding starts.
2. Stamped weld map. The weld map shows weld locations; each weld is stamped with the welder's stamp number. WPS reference is on the drawing.
3. Digital welder-to-WPS matching. Software cross-references welder WPQs to authorized WPSs and prevents assigning a welder to a procedure they can't qualify under. Foolproof, but requires investment.
Common traceability findings
- Production weld with no clear WPS reference on the drawing or weld map.
- Welder stamp present but the welder's WPQ doesn't cover this process or position.
- WPQ continuity gap > 6 months. Welder produced welds while not qualified.
- WPS revision changed; welder's WPQ tested against prior revision. Usually OK if essential variables didn't change, but should be documented.
- Welder stamp on welds, but the welder is no longer with the company and the stamp wasn't retired. Stamps must be retired when welders leave.
The audit-day trace
For each randomly selected weld:
- What WPS authorizes this weld?
- Is the WPS current? (cross-check the library)
- Who welded this? (stamp on the weld)
- Does the welder hold a current WPQ for this WPS's process, position, and thickness?
- Is the welder within the 6-month continuity window for this process?
All five must trace cleanly. Any one break is a finding.
A WPS tool that maintains welder-WPS authorization mappings — and refuses to assign work that can't trace — eliminates this entire failure mode.