Stud welding — specifically drawn-arc stud welding — accounts for tens of thousands of shear connector welds on every major structural steel project. It is fast, largely automated, and frequently overlooked in procedure qualification packages. AWS D1.1:2025 Clause 7 fills that gap with qualification requirements, production controls, and acceptance criteria that are separate from the groove and fillet weld procedures covered in Clause 5 and Clause 6.
Scope of Clause 7
Clause 7 applies to arc stud welding (both drawn-arc and capacitor-discharge methods) on structural steel. The most common application is headed shear connectors welded to the top flanges of steel beams to create composite action with a concrete slab. Other applications include threaded studs for railing attachment, Nelson pins, and anchor-type studs for PEMB connections.
Clause 7 does not govern resistance welding or friction-welded fasteners. Those fall outside the D1.1 scope entirely.
Procedure Variables
The stud welding procedure must document at minimum:
- Stud diameter and type — headed shear connectors follow AWS D1.1 Annex I dimensional requirements; threaded studs follow applicable ASTM specifications.
- Base metal — P-number equivalent and minimum thickness. Minimum base metal thickness is related to stud diameter; extremely thin flanges relative to stud diameter can cause inadequate fusion at the stud periphery.
- Lift and plunge settings — these are the gap the stud is lifted before arc initiation and the depth it is plunged back into the molten pool. Correct settings are the primary control over heat input and flash formation.
- Arc shield (ferrule) type — ceramic ferrules shape the flash and contain the arc. Through-deck applications require a specific ferrule geometry to accommodate the standing seam height of metal decking.
- Position — flat (1F) is the standard for shear connectors. Overhead (4F) requires separate qualification.
- Shielding gas — not required for short-stud CD welding but may be specified for drawn-arc studs in drafty environments.
A change in stud diameter, base metal group, or method (drawn-arc to CD) constitutes an essential variable change and requires re-qualification.
Qualification Testing
Qualification consists of welding a set of test studs and evaluating them through two methods:
Bend test. The stud is bent to 30° from its original axis using a pipe or tube as a bending bar. The weld is acceptable if there is a full flash at the root and no cracking in the weld metal or heat-affected zone. If a stud at 30° shows a crack, the engineer may require bending to 60° to confirm structural failure mode — a ductile fracture through the weld is preferable to a brittle HAZ crack.
Torque test. For threaded studs, a calibrated torque wrench loads the stud to a specified minimum torque. This supplements or replaces bend testing where bending is geometrically impractical.
Macro section examination (cross-section polish and etch) may be required by the engineer of record, particularly on critical connections or when process setup is being validated for the first time.
Production Control Test (PCT)
Unlike most structural welding where the WPS is qualified once and production begins, stud welding relies on in-process quality controls called production control tests. The PCT requirements in Clause 7 are:
- Start of shift: weld five consecutive test studs to a piece of runoff plate or sacrificial steel before welding production studs.
- When conditions change: any change in equipment, personnel, environment (wind, temperature), or deck thickness triggers a new PCT before continuing.
- Bend each PCT stud to 30°. All five must pass before production resumes.
If any PCT stud fails, the cause must be identified, the equipment or settings corrected, and a new five-stud PCT completed successfully. This is the mechanism that ensures the welder, gun, and controller are dialed in before a single production stud goes down.
PCTs are a documentation artifact. The QC record for a stud-welded job should show a PCT log correlating each production run to a passing five-stud test. Third-party inspectors and AISC auditors will ask for this log.