A WPS that lists a single row of filler metal, current range, and voltage range is technically a WPS—but for a multi-pass CJP groove weld, it may not actually control what happens at the arc. A root pass on a CJP joint looks nothing like a fill pass in the same groove: smaller electrode, lower amperage, different travel speed, different heat input. Documenting them with one row creates a qualification gap that surfaces during audits, or worse, during post-failure analysis.

Root, hot, fill, and cap: four different welding events

In a typical multi-pass CJP groove weld, four distinct pass types appear:

Root pass. Least forgiving. A fusion defect or lack-of-penetration at the root propagates through the joint under fatigue loading. Root passes typically use a smaller electrode diameter (SMAW) or reduced wire feed speed (GMAW/FCAW) and lower heat input to control penetration. Burn-through is the primary risk on open-root joints; cold lap on backing.

Hot pass. Deposited immediately after the root, the hot pass ties the root bead into the fill and burns out any slag trapped at the root toe. It runs slightly hotter than the root to ensure fusion but the interpass window is narrow—too cold and you get cold lap; too hot and you push the interpass temperature toward its maximum.

Fill passes. The bulk of the weld volume. Higher current, larger wire or electrode, faster travel, maximum deposition rate. Parameters are optimized for productivity. This is where most shops document their WPS parameters because it's the longest part of the welding sequence.

Cap passes. The visible surface. Cap passes often run at slightly reduced heat input and current to control crown height and avoid undercutting the toes. Profile defects—undercut, overlap, excessive reinforcement—are most visible here and most likely to be flagged on visual inspection.

Each pass type has its own optimal parameters. Documenting them all with one row leaves the CWI, the welder, and any future auditor without a reference point for what parameters were actually qualified.

Heat input as the controlling variable

Heat input is an essential variable under AWS D1.1:2025 Table 6.6. The standard formula:

Heat Input (kJ/in) = (Amperes × Volts × 60) / Travel Speed (in/min) ÷ 1000

Consider a 3/8 in CJP groove weld welded SMAW:

  • Root pass: 3/32 in E7018, 90 A / 22 V / 5 ipm → heat input ≈ 23.8 kJ/in
  • Fill pass: 1/8 in E7018, 145 A / 23 V / 8 ipm → heat input ≈ 25.0 kJ/in

Both values must fall within the PQR-qualified heat input range. If the PQR was run at 24–27 kJ/in and the root pass produces 23.8 kJ/in, the root pass is outside the qualified range—even though a lower heat input might seem conservative. The essential variable is a window with both a minimum and a maximum, not just a ceiling.

Rule library based on AWS D1.1:2025; verify against your governing edition.

When CVN testing is required, AWS D1.1:2025 Table 6.8 supplementary essential variables add tighter constraints on heat input changes. For CVN-required work, even modest pass-to-pass variation in heat input can cross a Table 6.8 threshold. See CVN impact testing and AWS D1.1:2025 Table 6.8 for those supplementary requirements.

For a full review of Table 6.6 and what each row requires, see AWS D1.1:2025 Table 6.6 explained.

Interpass temperature between passes

The WPS specifies a maximum interpass temperature. Production welding must stay within it. For pass-sequence work, this means:

  • Preheat is established before the root pass and maintained at or above the minimum between all subsequent passes.
  • Interpass temperature is measured on the base metal near the joint immediately before starting each new pass.
  • If the measured temperature exceeds the WPS maximum, welding stops. The joint cools to within range before the next pass begins.
  • Production logs on CVN-required work, seismic demand-critical welds, and high-strength steel joints typically require the inspector or welder to record the interpass reading for each pass.

The connection between interpass temperature and pass sequence is direct: a welder moving fast between passes in a thick joint may not allow enough cooling time, pushing interpass above the maximum. A WPS that documents the pass sequence with expected pass times gives both the welder and the inspector a realistic reference.

For how preheat and interpass temperature are documented and verified, see Preheat and interpass temperature: how to document on a WPS.

What the PQR should have recorded

When the PQR was run, the test welder should have recorded actual parameters for each pass type. That is the evidence that the qualified range actually covers real production practice. A PQR with a single data row—likely from the fill passes where the welder spent the most time—may not have qualified root-pass parameters at all.

A well-structured PQR records for each pass:

  • Pass designation (R, H, F1, F2, ..., Cap)
  • Electrode or wire classification and diameter
  • Amperage and polarity
  • Voltage
  • Travel speed
  • Heat input calculated
  • Interpass temperature measured before starting the pass

That is the audit trail a WPS can point back to when production parameters are questioned.

The problem with legacy WPS templates

Most WPS templates circulating in fab shops are single-row forms inherited from earlier editions. They have one line for process, one for filler metal, a range for amperage, a range for voltage. They were designed around single-pass fillet welds or were never updated when the shop moved to heavier sections.

Applied to a 1-inch CJP column splice with eight or ten passes, the single-row form is inadequate. The listed range might technically span root and fill parameters, but that only holds if the PQR was run across that full range—which is uncommon. More often the range was copied from a previous WPS or estimated, and no one compared it to the actual PQR heat input data.

Digital WPS forms with a structured passes table address this directly. Each pass type gets its own row: electrode diameter, current range, voltage range, travel speed range, and computed heat input range. The system calculates heat input from the entered values and flags any row where the resulting range falls outside the supporting PQR envelope. That moves the check from the audit to the WPS drafting step.

What inspectors check at pass hold points

A CWI on a multi-pass structural joint typically works from three hold points:

  1. Fit-up inspection. Before any welding. Joint geometry, root opening, alignment, cleanliness.
  2. Root inspection. After the root pass and before any fill. The CWI checks the root bead visually, and on complete-penetration joints with a back-gouge requirement, inspects the back-gouge for complete removal of the root prior to filling from the second side.
  3. Final visual. After the cap pass. Profile, undercut, crater fill, arc strikes.

The pass sequence on the WPS tells the inspector what to expect at each hold point: what pass is being inspected, what electrode size and process were used, and what heat input range is expected. Without that reference, the inspection is disconnected from the documented procedure.

For documentation practices that keep the WPS-to-production chain intact across all pass types, see Weld map and WPS traceability in production. A full digital workflow that structures pass-by-pass documentation is available at pricing.